Molonglo River Bridge Crossing & John Gorton Drive Extension.

APG successfully delivered the project within the required timeline, handing over high-quality foundations that met the rigorous standards of a major ACT infrastructure development.

Australian Piling Group was awarded the critical piling works for the river bridge abutments and the protection of existing Motorist Variable Message Sign (MVIS) structures. This project is a key component of the John Gorton Drive Extension, providing a vital transport link across the Molonglo River.

Phase A: Bridge Abutment Foundations

When the load-bearing soil or rock is located at significant depths. APG utilises modern track-mounted rigs equipped with Kelly bars to achieve depths of up to 50 linear metres, ensuring structural stability for the heaviest loads.

Critical Infrastructure Proximity

When the load-bearing soil or rock is located at significant depths. APG utilises modern track-mounted rigs equipped with Kelly bars to achieve depths of up to 50 linear metres, ensuring structural stability for the heaviest loads.

On-Site: Molonglo River Bridge

Project Track Record

Adelaide, SA

Torrens to Darlington (T2D) Project

  • Torrens to Darlington (T2D) Project
  • Adelaide, SA

Australian Piling Group (APG) is delivering complex piling and foundation works across the Southern Tunnel & Surface Package (STSP), Norther...

Key Challenge

Live Traffic & Constrained Work Areas, Night Works Operations, High-Precision Reinforcement Cage Installation, Multi-Pac...

Sydney, NSW

Eastern Tunnelling Package

  • Eastern Tunnelling Package
  • Sydney, NSW

Australian Piling Group (APG) was engaged to deliver the foundation king piles for the Eastern Tunnelling Package of Sydney Metro West, cove...

Key Challenge

Hard Ground Conditions, Constrained Urban Environment, Major Rig Cranage Operations, High Tolerance Requirements

Sydney, NSW

Sydney Metro West - Surface Civil And Alignment Works (SCAW)

  • Sydney Metro West - Surface Civil And Alignment Works (SCAW)
  • Sydney, NSW

Australian Piling Group (APG) was engaged to deliver the foundation piling works for the Surface Civil and Alignment Works (SCAW) package of...

Key Challenges

Accelerated Programme Delivery | Complex Reinforcement Cage Installation | Large-Diameter Foundation Construction | Com...

2 min read